Weekly Construction Update – As part of the Richland Airport Electrical Replacement Project, the Port will be issuing these weekly construction updates to keep the Airport users as

well informed as possible in our attempt to limit the impact on airport users.

Construction Schedule for the week of August 15, 2022

The contractor has moved to the west end of Runway 8-26 for most of their work this week.  Runway 8-26 and Taxiway B will be closed Monday morning, August 15 beginning at 6

a.m., and will be signed closed at both ends of the runway intersection.  

Navigation lights on 8-26 and Taxiway B will continue to be off until the end of September.

Runway 8-26 will be reopened for the weekend no later than 4 p.m., Friday, August 19th.  

The contractor may be crossing Runway 1-19 at Taxiway B, however, this should be very limited.

Portions of Taxiway B, east of Runway 1-19 will remain closed for the weekend to facilitate construction, however, full use of Runway 8-26 will still be available.

Pilots should continue to use caution when taxiing and during landings/takeoffs.

Also, please note that the FAA-controlled Medium Intensity Approach Lighting System (MALS) off the end of Runway 19 is temporarily out of service due to an underground wiring

failure.  In order to keep Runway 1-19 fully opened, the repair to the MALS will not happen until after September 6th during the intersection closure.  

Weekly Construction Update – As part of the Richland Airport Electrical Replacement Project, the Port will be issuing these weekly construction updates to keep the Airport users as

well informed as possible in our attempt to limit the impact on airport users.

Construction Schedule for the week of August 15, 2022

The contractor has moved to the west end of Runway 8-26 for most of their work this week.  Runway 8-26 and Taxiway B will be closed Monday morning, August 15 beginning at 6

a.m., and will be signed closed at both ends of the runway intersection.  

Navigation lights on 8-26 and Taxiway B will continue to be off until the end of September.

The contractor may be crossing Runway 1-19 at Taxiway B, however, this should be very limited.

Portions of Taxiway B, east of Runway 1-19 will remain closed for the weekend to facilitate construction, however, full use of Runway 8-26 will still be available.

Pilots should continue to use caution when taxiing and during landings/takeoffs.

Also, please note that the FAA-controlled Medium Intensity Approach Lighting System (MALS) off the end of Runway 19 is temporarily out of service due to an underground wiring

failure.  In order to keep Runway 1-19 fully opened, the repair to the MALS will not happen until after September 6th during the intersection closure.  

Original source can be found here.



Related

Keith Goehner, Washington State Senator for the 12th District

Washington Senate passes income-tax bill amid high public opposition

The Washington State Senate has passed a bill that would create a state income tax, moving it forward despite significant opposition and record public engagement.

Keith Goehner, Washington State Senator for the 12th District

Senator Keith Goehner discusses key issues at start of 2026 legislative session

Senator Keith Goehner spoke with KOZI Radio as the 2026 legislative session began, addressing several topics including revenue challenges, potential changes to income tax policy, restrictions on citizen initiatives, law enforcement oversight, and…

Keith Goehner, Washington State Senator for the 12th District

Goehner criticizes governor’s $244 million plan as insufficient for solving state’s housing shortage

Senator Keith Goehner, the ranking Republican on the Washington State Senate Housing Committee, has voiced concerns over Governor Ferguson’s recently announced $244 million housing plan.

Trending

The Weekly Newsletter

Sign-up for the Weekly Newsletter from Wenatchee Times.